Roughly $15 to $25 billion
Roughly $15–25 billion, depending on inflation and project delivery methods.

That range covers separating all 223 places where the A, E and K Lines currently cross car traffic at street level — by raising the tracks onto a viaduct, lowering them into a trench, or bridging the road over them — plus the longer platforms that let Metro run 6-car trains. The low end assumes steady prices and fast, bundled contracts; the high end assumes higher inflation and one-crossing-at-a-time delivery.
For scale: Melbourne is doing the same thing right now
$15–25B · 10 years
≈ A$15.3B (≈ US$10B) · 2015–2030
Melbourne has already removed 88 of 110 crossings, rebuilt 40 stations, and is on schedule to finish in 2030. Their per-crossing cost lands in the same range as this projection — and voters there have re-elected the program twice.
Sources: Justin Levy, LaXing financial projection (Sept 2026); Victoria's Big Build — Level Crossing Removal Project; Victorian Auditor-General cost estimates. Per-crossing and per-year figures are simple division of the projection range and are illustrative.
From road and freeway funds voters already approved
Initially $9 billion is transferred from roadway projects. Because Measure M has no sunset date, more funding can be allocated when needed, and numerous Federal and State grants can help. In addition to roadway funding, Local Return funds — which often get used for road improvement programs — will also be allocated to this project.

In plain terms: Los Angeles County already collects two half-cent sales taxes for transportation, Measure R (2008) and Measure M (2016). Both set aside a fixed share for highway construction, and both send a share back to cities as "Local Return," which cities mostly spend repaving streets. The initiative redirects those road dollars into grade separation for ten years. Measure M never expires, so the road programs are paused, not cancelled — they resume once the trains are separated.
The bar shows the order in which sources are drawn on, not exact proportions; only the $9B figure is fixed in the projection. The remaining $6–16B is covered by the other three sources in combination.
What $9 billion of road money looks like
Metro's own budget puts this in perspective. For the fiscal year that started July 2026, Metro plans to spend $887 million widening freeways — up 40% on the year before. Ten years of that single line item is the whole down payment.
× 10 years ≈ $8.9B
Sources: Justin Levy projection; Streetsblog LA, March 20 2026 (Metro FY26–27 Highway Multimodal Program: $157.5M capacity, $340.5M Express/HOV, $335.1M subregional, $46M bus); Metro Measure M (no-sunset half-cent sales tax).
Highways still get most of it — at every level of government
The case for redirecting road money rests on a simple fact: roads and freeways already receive the lion's share of transportation dollars flowing into Los Angeles. Four snapshots, federal to local:

View as table
| Program | 5-year total |
|---|---|
| Federal-aid highways | $25.3B |
| Public transit | $9.45B |
View as table
| Program | 2025–26 |
|---|---|
| Caltrans | $16.1B |
| Local streets & roads | $3.7B |
| Transit & Intercity Rail Capital | $1.56B |
| State Transit Assistance | $1.09B |
| High-Speed Rail Authority | $0.8B |
View as table
| Subfund | Share | 40-year total |
|---|---|---|
| Transit construction | 35% | $41.9B |
| Transit operations | 20% | $23.9B |
| Highway construction | 17% | $20.3B |
| Local Return | 16% | $19.1B |
| Metro rail ops, good repair, ADA, active transportation, regional rail | 12% | $16.2B |
View as table
| Line item | FY 2026–27 |
|---|---|
| Bus & rail operations | ~$3.0B |
| Transit infrastructure development | $2.0B |
| Regional allocations & pass-through | $1.8B |
| Freeway expansion | $0.887B |
Ten years of road money moves to the rails — then moves back
Metro is given a 10-year time frame to complete the project, and the funding comes from roadway and highway projects.

Nothing about the taxes changes. What changes is the order of the queue: for one decade, the highway construction and Local Return dollars that would have widened freeways and repaved streets are spent lifting the trains out of traffic first. Because Measure M has no end date, the road programs pick up again afterwards — with faster trains carrying more of the people who used to be stuck in the same traffic.
Illustrative. Today's roads figure is Metro's FY 2026–27 freeway-expansion budget; the per-year separation figure is the $15–25B projection divided over ten years. The 2028 ballot and 10-year deadline come from the draft LA County Safe and Efficient Light Rail Grade Separation Act.
Roughly 18,000 to 22,000 jobs a year, for ten years
Using a standard RIMS II distribution for heavy civil construction in urban Los Angeles County:

Source: Justin Levy, LaXing financial projection (Sept 2026), applying RIMS II multipliers for heavy civil construction in Los Angeles County.
Quick answers
Separations are built alongside or above running tracks, one corridor at a time — the same way the E Line's existing bridges were built. Melbourne kept its trains running through 88 removals.
Red-light delays alone add up to about 20 minutes on a street-running trip today, on top of the slow zones and stop-and-go that come with sharing pavement. Long Beach to downtown falls from 57 minutes toward 30.
Measure R and Measure M are already on the books. The initiative re-sequences how their road and Local Return dollars are spent for ten years.
Measure M has no sunset date, so highway and street programs restart after the separations are finished — and Metro can borrow against future years if the build runs over $9B.